St. Louis County marks the end of project that brought fixes to 21 bridges and culverts

Dubbed the “bridge bundling project,” it was a three-year, $25 million collaboration between the northern Minnesota county and the Minnesota Department of Transportation.

The Minnesota Star Tribune
November 14, 2024 at 1:04PM
St. Louis County and the Minnesota Department of Transportation marked the end of a bridge bundling project that brought fixes to 21 spots in northern Minnesota. With before and after photos behind him, Matt Hemmila, from the county, went through the three-year project's timeline during a news conference at the Public Works building in Rice Lake.

RICE LAKE, MINN. – Before and after photographs decorated the side of a construction vehicle parked in a St. Louis County Public Works garage Wednesday morning, marking the ceremonial end of a years-long project to replace aged bridges and culverts within northern Minnesota.

The more than $25 million bridge bundling project, a collaboration between the county and the Minnesota Department of Transportation, brought fixes to 17 spots in St. Louis County and four in neighboring Carlton County. The finale was a bridge on West Skyline Parkway leading to Spirit Mountain, which opened in mid-October — a month earlier than expected.

It was the largest road and bridge construction contract that this county has seen, according to 5th District County Commissioner Keith Musolf, who chairs the Public Works and Transportation committee.

“Replacing these bridges has made our region a safer place, strengthened our ability to withstand the environment of northern Minnesota’s weather and the events that have occurred over the past few seasons,” he said during a press conference.

The partnering entities started collecting funding for the project in 2018 when the Federal Highway Administration solicited applications for a project that would bundle bridge work, with a goal of demonstrating cost savings, according to Matt Hemmila, St. Louis County’s deputy director of engineering.

They were able to secure $10.2 million, then tacked on more federal, state and local funds for the rest. Hemmila estimated they saved between 10% and 15% on the cost of bridge fixes by not tending to each individually.

“So I think the program was a success,” he said.

Areas that saw upgrades, starting in 2022, include a spot on Normanna Road, over the French River, Munger Shaw Road over Bug Creek, and Three Lakes Road over Boulder Creek. There were two projects on Kensington Drive and two on Hwy. 210 that cross the Tamarack River. The only project this year was over Knowlton Creek on West Skyline Parkway, which included stream restoration work. St. Louis County has a two-minute video that shows before and after photos from each location.

Local architect and engineering firm LHB designed the new bridges and Redstone Construction of Mora, Minn., handled the construction.

about the writer

about the writer

Christa Lawler

Duluth Reporter

Christa Lawler covers Duluth and surrounding areas for the Star Tribune. Sign up to receive the new North Report newsletter.

See More

More from Duluth

card image

In his successful campaign for mayor last year, Roger Reinert criticized incumbent Emily Larson for choosing a Twin Cities firm over locally connected groups to market the city. Now the city is looking outside Minnesota.