It's Warren Buffett vs. Big Tech in Iowa's latest wind-farm debate

Facebook, Google and Microsoft — which all have data centers in Iowa — say MidAmerican Energy's $4 billion proposal could drive up costs for customers.

By Mark Chediak

Bloomberg News
June 10, 2022 at 8:47PM
MidAmerican Energy, backed by Warren Buffett’s Berkshire Hathaway, has proposed a complex of wind farms in Iowa that would be the largest in the U.S. (Matt Young, Associated Press/The Minnesota Star Tribune)

Google, Facebook and Microsoft — three of the world's biggest corporate buyers of clean power — are sounding the alarm that a nearly $4 billion, Warren Buffett-backed renewable-energy project proposed in Iowa isn't necessarily in the best interest of customers, including them.

If approved, it would be the largest complex of wind farms in the entire country when it comes online by the end of 2024, producing enough electricity for more than 700,000 homes. MidAmerican Energy, a utility owned by Buffett conglomerate Berkshire Hathaway Inc., has asked state regulators to approve terms including a guaranteed 11.25% rate of return before starting construction on a project it says will help in its efforts to trim carbon emissions by 75% compared with 2005 levels.

But the big-name tech giants that operate data centers in the state warn the project, dubbed Wind Prime, could drive up electricity costs. MidAmerican, they say, should consider alternatives.

"We have concerns that the current Wind Prime proposal is not in the energy customers' best interest," Corina Standiford, a spokeswoman for Google, said in an e-mail.

The fight is an important one to watch because it demonstrates the increasing influence technology giants have on the energy transition. Tech companies have pushed utilities in other parts of the U.S. to offer more clean energy options as they seek to clean up the sources of power for their energy-intensive operations. And since they buy so much power, the utilities often listen to them.

"The scale that these companies are buying green power at is massive," said Kyle Harrison, an analyst with BloombergNEF. As technology companies have become bigger and bigger consumers of renewable energy, they've also become more sensitive to its cost, he said.

MidAmerican, based in Des Moines, proposed the project in January, laying out a sweeping plan for about 2,000 megawatts of wind power and 50 megawatts of solar generation. The company — which derives about 58% of its power in Iowa from wind and 42% from coal, nuclear and other sources — said Wind Prime is a key piece of the company's goal to reach net-zero emissions.

Facebook, which also buys large amounts of power to run data centers in Iowa, referred to the proposed project in a joint regulatory filing with Google as an "exceedingly costly, massive increase in generation that MidAmerican has not demonstrated is necessary."

Last month, Microsoft filed its own petition with the Iowa Utilities Board saying it planned to join the tech-customer coalition.

Facebook parent Meta Platforms and Microsoft declined to comment beyond their filings.

Of course, the pushback from the tech giants doesn't necessarily mean they won't ultimately support it — or buy its power if it comes to fruition. Any multibillion-dollar power-plant project is bound to trigger some back and forth, even heated debate, among customers, environmental and consumer groups and others. Regulators could approve MidAmerican's proposed terms for the project, call for changes to them or reject it altogether.

Standiford, the Google spokeswoman, said the company is committed to run its Iowa data center — one of the company's largest — on 100% carbon-free power and supports "new, cost-effective sources" of clean energy.

"We are actively working with regulators and MidAmerican to ensure the right investment for Iowa," she said.

about the writer

Mark Chediak

More from Business

Dr. Shruti K. Gohil, associate medical director for epidemiology and infection prevention at UCI Medical Center, holds a dose of MMR, the vaccine against measles, mumps and rubella. (Ana Venegas/Orange County Register/TNS) ORG XMIT: 1163174 ORG XMIT: MIN1501282305177647 ORG XMIT: MIN1502031200399233

Health officials say the recent outbreak of the highly contagious virus looked bad this summer, but optimism is growing they may have contained it.

Light and dark arrows pointing in opposite directions over a file photo of white and black school children in the 1950s.
card image